Portugal's Simplex Urbanístico: what Decree-Law 10/2024 changed and what the 2026 revision reversed

The Simplex planning reform's measures and when each took effect, what survived after October 1, 2026, what Decree-Law 108/2026 changed, and what it means for building work, titles and sales from 2024 to 2026.

Simplex Urbanístico is the popular name for Decree-Law 10/2024 of January 8, the Portuguese reform that from 2024 abolished paper permits (alvarás) and the use permit after permitted work, widened the range of exempt work, introduced tacit approval of building permits and stopped requiring the habitation license at the deed. The revision of the RJUE (Regime Jurídico da Urbanização e Edificação, Portugal's planning and building code) by Decree-Law 108/2026, in force since October 1, 2026, kept the overall direction but corrected or reversed several of those measures: overall permit deadlines, the exemption for extensions, titles made up of payment receipts alone, the bare warning at the deed, and the repeal of the RGEU in June 2026. This guide sets out the dates, what stayed, what changed again and what it means if you built, applied for permits or sold between 2024 and 2026.

To apply these checks to a property in Porto or elsewhere in Portugal, see our prior information request and building legalization services.

01 What the Simplex Urbanístico is

Decree-Law 10/2024 was adopted under the legislative authorization in Law 50/2023 of August 28 and delivers a reform set out in Portugal's Recovery and Resilience Plan. Its preamble frames it as part of the SIMPLEX program, with a "zero licensing" approach: abolishing unnecessary permits, authorizations and administrative acts, making procedures uniform across municipalities, and making new housing faster and cheaper to deliver.

It is not a standalone regime. It is a decree-law that amended other laws: mainly the RJUE (Decree-Law 555/99), but also the RGEU (Regulamento Geral das Edificações Urbanas, the 1951 general building regulation), the Portuguese Civil Code, the framework law on land use and planning, the rules on planning instruments (RJIGT), the urban regeneration regime and the rules on heritage protection zones. That is why the question "is the Simplex still in force?" has to be answered measure by measure.

The rules in force since October 1, 2026, procedure by procedure, are in the guide on the RJUE in 2026. This guide covers the sequence: what the Simplex did, when, and what happened to it in the revision.

02 Key dates for the Simplex and the 2026 revision

The Simplex did not take effect all at once. Article 26 of Decree-Law 10/2024 set several dates, and the 2026 revision added more. The date that matters for most building work is March 4, 2024; for the deed, January 1, 2024.

Timeline of the Simplex Urbanístico and the RJUE revision
DateWhat took effectLegal basis
January 1, 2024New exemptions and minor works, changes to the RGEU and the Civil Code, the end of mandatory police presence at works, and the end of showing the use permit and the home's technical file (ficha técnica da habitação) at the deedDecree-Law 10/2024, Art. 26(a) to (f)
March 4, 2024General regime: comunicação prévia (prior notice) mandatory where it applies, tacit approval of permits, end of paper permits, new building-use rules, PIP valid for 2 yearsDecree-Law 10/2024, Art. 26
April 8, 2024Each municipality's planning bylaws made available on the Diário da República (official gazette) websiteDecree-Law 10/2024, Art. 26(g)
January 6, 2025Requests for opinions from public bodies must go through the electronic opinions systemDecree-Law 10/2024, Art. 26(h)
January 5, 2026Planned date for the national online planning platformDecree-Law 10/2024, Art. 26(i)
June 1, 2026Date set for repealing the RGEU; the amendment postponing it took effect that same dayDecree-Law 10/2024, Art. 25, and Decree-Law 108/2026, Art. 13(2)
October 1, 2026Revision and republication of the RJUEDecree-Law 108/2026 and Decree-Law 155-B/2026
January 1, 2030Architectural designs must be filed in BIM (Building Information Modeling)Decree-Law 10/2024, Art. 17(1)

03 What the Simplex changed for building work and procedures

For building work and municipal procedures, these were the 2024 measures with the most practical effect:

  • More exempt work: rebuilding and extensions that did not raise the façade height, even if they added floors and usable area, no longer needed a permit or prior notice; the same went for interior work affecting the structure, with a professional's statement of responsibility, and for replacing window frames with more efficient ones that look the same from outside (RJUE Articles 6(1)(b) and (e) and 6-A(1)(j)).
  • Prior notice made mandatory: if a project fell under comunicação prévia you could no longer opt for a permit, and execution units with certain parameters also qualified for comunicação prévia (Article 4).
  • Tacit approval of permits: the câmara municipal (municipal council) was given an overall deadline of 120 days (up to 300 m² of gross floor area), 150 days (up to 2,200 m² and listed buildings) or 200 days (larger projects, subdivisions and infrastructure works), counted from filing, after which the permit was tacitly approved (Article 23).
  • No more paper permits: a permit was evidenced by the fee payment receipt, and a prior notice by proof of filing (RJUE Article 74 and Decree-Law 10/2024, Article 21).
  • PIP: a favorable PIP (pedido de informação prévia, a binding prior information request) became valid for 2 years, plus 1 year with a confirming declaration, and a PIP that assessed the items in Article 14(2), or covered an area with a detailed plan or subdivision, exempted the work (Article 17).
  • Less review and less paperwork: the council stopped reviewing building interiors and engineering designs, and could no longer ask for documents not listed in the ministerial order, such as the caderneta predial (property tax record) or copies of documents it already holds (Articles 3, 9(12) and 20).
  • Completeness check: if the council did not ask for corrections or reject the application outright, it counted as complete and could not be refused for missing documents (Article 11(5)).
  • No mandatory police presence: police supervision could no longer be required at works, even when a street was closed (Article 40-A).

04 What the Simplex changed for building use, sales and housing

Beyond building work, the Simplex changed rules that matter to anyone buying, selling or changing the use of a property:

  • Use after building work: the use permit was replaced by filing the statement of responsibility from the site manager or supervising engineer and, if the design had changed, the as-built drawings; the building could be used immediately and the filing could not be refused (RJUE Article 62-A).
  • Change of use without work: handled through a comunicação prévia com prazo (prior notice with a waiting period), with use allowed 20 days after filing unless an inspection was ordered (Articles 62-B, 63 and 64).
  • The deed: from January 1, 2024, the use permit and the home's technical file no longer had to be shown; whoever executed the deed only warned the buyer that the property might lack planning titles (Decree-Law 10/2024, Article 19).
  • RGEU: a bidet was no longer mandatory, a shower was allowed instead of a bathtub, and kitchens could be merged with other rooms, except bathrooms, as kitchenettes, cupboard kitchens or walk-through kitchens (RGEU Articles 66 and 68). The RGEU itself was set to be repealed on June 1, 2026.
  • Condominiums: changing a unit's use to housing no longer needed the other owners' approval (Portuguese Civil Code, Article 1422-B).
  • Land: fast-track procedures were created to reclassify rural land as urban for industry, logistics or housing (RJIGT Articles 72-A and 72-B), since amended, as explained in the guide on rural land that can become urban.

05 What the 2026 revision kept

Decree-Law 108/2026 did not repeal the Simplex. Its preamble acknowledges that the 2024 reform ran into problems of implementation and consistency, and presents the revision as an adjustment of its measures, to simplify with more legal certainty. Still in force, among others:

  • Tacit approval of permits, now at each stage of the procedure (RJUE Articles 20(12) and 23(1)).
  • No option to choose a permit when the work falls under comunicação prévia (Article 4(6)).
  • The 2-year validity of a favorable PIP, plus 1 year with a declaration that the underlying facts and rules still hold (Article 17(5) to (7)).
  • The end of paper permits: references to alvarás now read as references to the operation's title (Decree-Law 108/2026, Article 9(3)).
  • The end of council-issued use permits, now complete: building use is always covered by a notice (Decree-Law 108/2026, Article 9(2)).
  • The list of documents councils cannot require, such as the caderneta predial or copies of documents they already hold, and the rule that interiors and engineering designs are covered by the professionals' statements of responsibility, without prior review (Articles 9(12) and 20(8)).
  • The 2024 changes to the RGEU and the Civil Code rule on changing a unit's use to housing, which the revision left untouched.
  • The requirement to file architectural designs in BIM from January 1, 2030 (Decree-Law 10/2024, Article 17(1)).

06 Why Decree-Law 108/2026 changed the Simplex

The preamble to Decree-Law 108/2026 explains the corrections. On comunicação prévia, it admits that it had stopped being real prior control, because the council only checked the paperwork formally during the completeness check; so it scrapped that stage and now requires the work to be in an area where the planning parameters are actually defined. On permits, it finds that deadlines tied to gross floor area did not reflect real complexity, and brings back stage-by-stage deadlines that can be extended for complex projects.

On titles, it takes the view that a payment receipt alone does not say what was authorized, and brings back a title that includes a summary of the operation, so that it holds up with third parties and in property transactions. On the deed, it seeks a balance between legal certainty and freedom to transact: you can still buy a property with no title, but the deed itself tells you so. And on the RGEU, it ties the repeal to the entry into force of new technical building rules, to be drafted with the professional bodies.

07 What the 2026 revision changed or reversed

The table compares the measures that changed again. The right-hand column is the regime for procedures started on or after October 1, 2026, and for those still in the completeness check on that date.

The full regime now in force, with each stage's deadlines, is in the guide on the RJUE in 2026. If you have an application filed before October 2026, or work done under the Simplex rules, a prior information request gets you the council's written position under the current rules.

Simplex Urbanístico versus the rules in force since October 1, 2026
TopicSimplex (Decree-Law 10/2024)Since October 1, 2026 (Decree-Law 108/2026)
Permit deadlinesOverall deadline of 120, 150 or 200 days from filing, depending on gross floor areaStage-by-stage deadlines: completeness check within 20 days, architecture in 30 and final decision in 20 (building work), with tacit approval at each stage (Arts. 11, 20 and 23)
Rebuilding and extensionsExempt if the façade height did not increase, even with extra floors and usable areaOnly rebuilding that restores the last valid precedent is exempt; adding floor area, height or volume is an extension, requiring a permit or prior notice (Arts. 2 and 6(1)(e))
PIP that exempts the workPIP covering the items in Art. 14(2), or in an area with a detailed plan, subdivision or execution unitOnly a full PIP that assesses every applicable item, and never for building use (Arts. 6(1)(h) and 17(2))
When PIP validity starts2 years from the favorable decision2 years from notification or tacit approval, for both kinds of PIP (Art. 17(5))
TitleFee receipt (permit) or proof of filing (prior notice)Application or form with a summary of the operation, proof of fees and notice of approval or proof of filing (Art. 4-A)
Use after building workFiling the site manager's statement and, if the design changed, as-built drawings; could not be refusedComunicação prévia on the official form, with a statement of responsibility and follow-up review (Art. 62-A)
Change of use without workPrior notice with a 20-day wait; the council could only order an inspectionPrior notice with a 10-day wait; the council can reject it or order an inspection (Arts. 62-B and 64)
The deedA warning that the property might lack planning titlesA statement that the title was shown, or that the seller declares having it or not having it; without it, the sale can be annulled (Art. 4-A(14))
Interior work affecting the structureExempt with a statement of responsibility, to be shown on inspectionExempt with a structural design, a statement and, where required, seismic strengthening, filed with the start-of-work notice (Art. 6(1)(b))
Design changes after the hearing stageAllowed to fix nonconformitiesOne filing only for permits; none for a PIP (Art. 24-A and preamble)
Fine for work without a titleDropped for work requiring a permit (repeal of Art. 98(1)(a))Restored: €500 to €200,000 for individuals and €1,500 to €450,000 for companies (Art. 98(1)(r) and (2))
Repeal of the RGEUOn June 1, 2026Only when the law with the technical building rules takes effect (Decree-Law 10/2024, Art. 25, as amended in 2026)
National online platformMandatory from January 5, 2026Mandatory once it is available (Art. 8-A)
Paying feesMunicipal bylaws could provide no method other than the single payment slip through the public administration payment platformAlso by transfer to the municipality's IBAN or through municipal platforms; self-assessment extended to tacit approvals (Art. 117(5) and (6))
Police presence at worksNever requiredRequired only when essential for traffic or safety where a street is closed, with 10 days' notice of the closure (Art. 40-A)

08 Work, titles and sales from 2024 to 2026: what it means today

The revision does not undo what was done under the Simplex. The new rules apply to procedures started on or after October 1, 2026, and to those still in the completeness check on that date (Decree-Law 108/2026, Article 12); the new deadlines for lapse and nullity apply to everything, counted from that date, unless the old deadline ends sooner. That leads to a few typical situations:

  • Exempt work done between 2024 and 2026, such as an extension that did not raise the façade: if it met the exemption's conditions and the PDM (Plano Diretor Municipal, the municipal master plan), it needed no title, and the RJUE treats as the last valid precedent an operation that needed no title when it was done (Article 2(r)). Keep proof of the date and, if you filed one, of the start-of-work notice. New work on the same building follows today's rules.
  • Permit evidenced by a receipt: Decree-Law 108/2026 does not require those titles to be replaced. Keep the fee receipt with the decision or the proof of tacit approval, because that is what you will show at the deed or to the bank.
  • Building use handled between 2024 and 2026: filing the Article 62-A documents, or a prior notice with a waiting period that met no objection, allowed the building to be used; keep the proof of filing. The habitation license guide explains how to put together a home's use title.
  • PIP issued under the Simplex: valid for 2 years from the favorable decision, as explained in the PIP validity guide. If it exempted the work only because the site was in a detailed plan or subdivision area, check with the council whether the exemption still holds for work started after October 1, 2026.
  • Sales: until September 30, 2026, the warning was enough; since October 1, 2026, the deed must state the planning title position, even if the property or the work is old.
  • Work done without a title or differing from the design: the route is still building legalization, now with the fine for work without a title back in place.

09 Frequently asked questions

What is the Simplex Urbanístico?

It is Decree-Law 10/2024 of January 8, which simplified Portugal's permitting in planning, land use and industry. It amended the RJUE, the RGEU, the Civil Code and other laws, with most measures in force from March 4, 2024 and some from January 1, 2024.

Is the Simplex Urbanístico still in force?

In part. It was not repealed, but Decree-Law 108/2026 amended it, together with the RJUE, with effect from October 1, 2026. Tacit approval of permits, the 2-year PIP validity and the end of paper permits remain; the exemption for extensions, overall permit deadlines, titles made of receipts alone and the bare warning at the deed were reversed.

After the Simplex, do I need a habitation license to sell?

You have not had to show it since January 1, 2024. Since October 1, 2026, the deed must state that the planning title was shown or include the seller's declaration that they have it or do not have it; without that statement, the sale can be annulled.

Has the RGEU been repealed?

No. The Simplex set the repeal for June 1, 2026, but Decree-Law 108/2026 amended that rule with effect from the same day: the RGEU will only be repealed once the law with the technical building rules takes effect. The 2024 changes, such as the end of the mandatory bidet, remain.

Is an extension built without a permit in 2025, under the Simplex rules, illegal?

If it did not raise the façade height and complied with the PDM and other rules, it was exempt, and the RJUE treats it as the last valid precedent. A new extension after October 1, 2026 needs a permit or prior notice. Check the conditions against the municipal file before you sell or do more work.

Do the 120, 150 and 200-day deadlines still apply?

Not to new applications: since October 1, 2026, there are stage-by-stage deadlines. A permit application filed earlier only moved to the new rules if it was still in the completeness check on that date; otherwise, confirm the applicable deadline with the council.

10 Official sources consulted

The official sources are in Portuguese. Check the version in force before preparing a notice, project or application.

Want to find these guides more easily when you search on Google? Add Apto Group as a preferred source.

Related services. To apply to your property.

Keep reading.

  1. Portugal's RJUE in 2026: what it is and what changed under Decree-Law 108/2026 Portugal's planning and building code as in force since October 1, 2026: procedures, deadlines, PIP, comunicação prévia, building use, titles, the deed, legalization, fines and what happens to applications already filed.
  2. Portugal's habitation license (licença de utilização): what it is, what replaced it and how to sort out your home's use title What the licença or autorização de utilização is, what changed with the Simplex reform and the October 2026 RJUE revision, how to get a use title for an existing home today and what happens at the deed.
  3. Approved PIP validity in Portugal: how long it lasts and how to keep it from lapsing The two-year validity, what has to happen within it, the declaration that adds one more year, PIPs issued before October 1, 2026 and a change of holder.
  4. Building legalization in Portugal: how it works and when you need it The legalization procedure under article 102-A of Portugal's RJUE, step by step: when it applies, what the council can waive, fines, selling the property and what changed in October 2026.
  5. Can rustic land become urban land in Portugal? The legal routes to rezone rustic land as urban in Portugal, the special housing regime until 2028, excluded areas, lapse deadlines and what an owner can actually do.
  6. PIP, building permit or comunicação prévia: which procedure your project needs in Portugal What each procedure does under the RJUE as revised in 2026, when the law decides for you, when a PIP first is worth it and when a full PIP replaces the permit.

Have a property in mind? Tell us your idea.

We reply within about 2 hours during business hours, then prepare a proposal for your project.

geral@aptogroup.eu

Porto · Portugal

Contact details and request details
What is your situation? *