The PDM in force in Guimarães is the 1st revision of the Plano Diretor Municipal (the municipal master plan), published in the Diário da República, Portugal's official gazette, as Aviso n.º 6936/2015 of June 22, 2015, and in force since June 23, 2015, with three amendments between 2019 and 2021. The 2nd revision was approved by the Câmara Municipal (the city council) on September 14, 2026, and by the Assembleia Municipal (the municipal assembly) on September 28, 2026, but it only takes effect the day after it is published in the Diário da República, and as of November 1, 2026, we could not find that publication. This guide explains what is in force, what the revision changes, how to view the maps on the council's WebSIG, which rules apply to your plot and when it is worth filing a pedido de informação prévia (PIP), the council's binding pre-application ruling.

To apply these checks to a property in Guimarães, see our prior information request and building legalization services.

01 Which PDM is in force in Guimarães

The Plano Diretor Municipal (PDM) is the plan that zones all the land in a municipality; the general PDM guide explains how it works. In Guimarães, the plan in force is the 1st revision, approved by the Assembleia Municipal on May 4, 2015 (Deliberação n.º 45) and published as Aviso n.º 6936/2015 in Diário da República no. 119, 2nd series, on June 22, 2015. It took effect on June 23, 2015.

The plan is made up of the regulations and annexes, the planta de ordenamento (land-use map), with noise zoning as an annex, and the planta de condicionantes (constraints map), with annexes on burned areas and wildfire hazard and on noise conflict zones (article 3). It has been amended three times, all under the special regime for regularizing business activities (RERAE); the 2019 amendment republished the full regulations. The boundaries of the REN (Reserva Ecológica Nacional, the national ecological reserve), shown on the constraints map, were published by Portaria n.º 95/2016 and amended in 2016, 2018 and 2019.

Guimarães PDM: the 2015 revision and its amendments
Publication dateActWhat it did
June 22, 2015Aviso n.º 6936/2015Published the 1st revision of the PDM, in force since June 23, 2015
November 22, 2019Aviso n.º 18789/20191st amendment under the RERAE: added article 116 and republished the regulations
January 21, 2020Aviso n.º 1067/20202nd amendment under the RERAE
October 22, 2021Aviso n.º 20024/20213rd amendment under the RERAE, on map sheets 70-4 and 85-1

02 The 2nd revision: approved in September 2026 and awaiting publication

The revision began with a council decision on December 13, 2018 (Aviso n.º 1780/2019), with an estimated 18-month timeline. The draft was open for public consultation from June 4 to July 3, 2025, with an additional 14-day period opened in July. After the October 2025 local elections, the new council executive revoked, on November 24, 2025, the September 2025 decisions that had approved the response to public comments and the final draft, and it reviewed the submissions again.

The reworked draft was approved by the council on September 14, 2026, with the Socialist (PS) councillors abstaining, and by the Assembleia Municipal on September 28, 2026, with no votes against. The approved regulations take effect the day after publication in the Diário da República and repeal the 2015 PDM with its three amendments (articles 309 and 310). As of November 1, 2026, the council's "PDM em Vigor" page still lists the 2015 plan and we could not find the publication, so that is the plan that applies. Before you file an application, check the Diário da República to see whether the revision has been published.

2nd revision of the Guimarães PDM: the dates that matter
DateStageWhat happened
December 13, 2018StartThe council opens the 2nd revision (Aviso n.º 1780/2019 of January 31, 2019)
June 4 to July 3, 2025Public consultationAviso n.º 13511/2025/2; followed by an additional 14-day period (Aviso n.º 17954-A/2025/2)
November 24, 2025RevocationThe new executive revokes the September 2025 decisions on the final draft
September 14, 2026Câmara MunicipalApproves the reworked draft
September 28, 2026Assembleia MunicipalApproves the revision, with no votes against
Pending as of November 1, 2026PublicationThe plan takes effect the day after publication in the Diário da República

03 What changes with the new Guimarães PDM

The new plan adopts the zoning system of the RJIGT (Regime Jurídico dos Instrumentos de Gestão Territorial, the legal framework for land-use plans): land becomes either rustic or urban, and the "urbanizável" (developable) land of the 2015 plan disappears. According to the plan report of September 2026, urban land grows from 6,187.67 to 7,335.73 hectares, an extra 1,148.06 hectares (18.55%). Central areas shrink by 9.07%, largely because former developable areas that were never built on did not qualify as urban land, and low-density urban areas nearly triple.

The council also highlights land reserved for five new road links and the option to create 31 planning and management units. The figures are those of the approved draft; the version that counts is the one published in the Diário da República. The table shows the urban land categories that change most.

Urban land in Guimarães: 2015 PDM and approved revision (hectares)
Category2015 PDMApproved revision
Central area877.16797.62
Residential area (habitacional in the revision)3,422.723,456.74
Low-density urban area369.111,065.07
Business area896.251,057.69
Total urban land6,187.677,335.73

04 How to check the Guimarães PDM on the WebSIG

The council publishes the PDM on its WebSIG (sig.cm-guimaraes.pt), reached from the "Websig - mapas online" page, with modules for issuing maps, viewing the PDM in force and viewing the PDM revision. The "PDM em Vigor" page lists the notices published in the Diário da República, and the open data page offers the PDM as a WMS service for use in GIS software. The SNIT geoportal of the Direção-Geral do Território (DGT, the national land-use agency) lets you confirm the published version.

According to the council's manual, the PDM module issues maps that are valid for planning applications. The steps:

  • Find the property in the PDM module, using the base maps and aerial photos.
  • Outline the property with the draw-geometry tool, or upload a georeferenced DXF file with the outline from a topographic survey.
  • Set the scale to 1:5000, the one the manual specifies for planning applications.
  • Overlay the property on the zoning: the WebSIG shows the area of the property in each land category.
  • Generate the PDF named "Planta de Ordenamento"; in the print options you can choose PDF/A, which digital applications require.
  • Repeat for the constraints, turning the zoning layer off and the constraints on, and check in the revision module how the property is zoned in the new plan.

05 The rules in force for your plot and what the revision changes

The 2015 PDM already splits land into rural and urban, but within urban land it still separates developed land from developable land (article 8). The parameters are mostly site coverage, floor area and impervious cover ratios and facade heights. The table compares the most sought-after categories with the regulations approved in 2026, which only apply once published; the guide how much can I build on my land explains the terms.

On rural land, the 2015 PDM does not allow subdivisions except for tourism developments (article 45), and in agricultural areas, which match the RAN soils (Reserva Agrícola Nacional, the national farmland reserve), any building requires prior authorization from the competent authority (article 47). See what you can build on rustic land.

Key parameters: 2015 PDM and the revision approved in 2026
Category2015 PDM (in force)Approved revision (not yet in effect)
Central areas (área central urbana in the revision)Multi-unit buildings; site coverage up to 0.8 and impervious cover up to 0.9 (article 72)Site coverage up to 0.75 and impervious cover of 0.8 (article 86)
Residential areas (habitacionais in the revision)Detached house with up to 3 units or semi-detached with up to 2; site coverage 0.6, up to 0.8 where justified; facade 7 m, or 9 m with mixed use (article 74)Detached with up to 4 units or semi-detached with up to 3; site coverage 0.7; facade 7 m, 9 m or 12 m depending on the case (article 90)
Low-density urban areasMinimum plot of 1,500 m² with 20 m of frontage or 1,000 m² with 30 m; site coverage 0.3, up to 0.4; facade 7 m (article 76)Minimum plot of 800 m² with 15 m of frontage, or 500 m² with 12 m for infill; site coverage 0.4; facade 7 m (article 92)
Rural settlementsInfill only; floor area ratio 0.2; facade 7 m; up to 2 units (article 61)Infill only; site coverage 0.3 and floor area ratio 0.6; facade 7 m; up to 2 units (article 80)
Scattered building areasMinimum plot of 1,000 m² with 30 m of frontage; floor area ratio 0.15; facade 7 m (article 63)Minimum plot of 750 m² with 20 m of frontage; site coverage 0.20 and floor area ratio 0.40 (article 82)
Housing on agricultural landWith authorization from the competent authority; floor area ratio 0.025; facade 7 m (article 47)Agricultural production areas: site coverage 0.02 and floor area ratio 0.04; facade 7 m (article 60)

06 Developable land: what applies until publication

In the 2015 PDM, developable areas are expansion areas that can be built on through subdivision or construction if the project does not hinder development of neighboring land, builds any missing infrastructure and meets the parameters of the category (article 84). The approved revision abolishes this category: each plot becomes urban or rustic land, and only the revision map shows which.

While the 2015 plan remains in force, article 199 of the RJIGT applies, as worded by Law 53-A/2025: the rules for developable areas in plans that have not yet adopted the new zoning rules are suspended by decision of the CCDR (the regional coordination and development commission) after hearing the municipality, and the suspension cannot be ordered if the municipality shows that the revision is nearly complete. It does not cover, among others, areas that already have urban characteristics or lots whose parameters were already set by an approved PIP or architectural design. If your plot is on developable land, ask the council or CCDR Norte whether the suspension has been ordered and compare the current map with the revision map on the WebSIG; see urban or rustic land: how to check.

07 Existing buildings and older PIPs under the new plan

The approved regulations protect what already has a permit. Pre-existing rights include buildings and activities that did not need a license and, while still valid, rights arising from licenses, prior notices, favorable PIPs and approved architectural designs (article 47). A favorable PIP obtained under the 2015 PDM and still within its validity period therefore keeps counting after the revision takes effect.

Lawful buildings that do not comply with the new plan can be altered, extended or changed in use, including one additional unit, if the works do not worsen the non-compliance, respect easements and improve living or sanitary conditions. The extension cannot exceed 50% of the floor area where that area is under 100 m², or 30% in other cases (article 47, no. 4). For unpermitted works, see legalizing an old house and outbuildings.

08 When to file a PIP in Guimarães

Reading the PDM gives you an interpretation; a decision on a pedido de informação prévia (PIP) gives you an answer that binds the council. Under the RJUE (Regime Jurídico da Urbanização e Edificação, Portugal's planning and building code) as revised by Decree-Law 108/2026, in force since October 1, 2026, the council decides a simple PIP within 15 days and a broad-scope PIP within 30 days (45 for subdivisions), counted from the end of the initial review; if it misses the deadline, the request is deemed approved, and a favorable answer gives you 2 years to file the license application or notice. The PIP guide explains the rules.

In Guimarães, applications are filed on the council's Urbanismo Digital platform (ud.cm-guimaraes.pt) after registering, and the zoning and constraints maps can be issued on the WebSIG. Until the revision is published, an application is assessed under the 2015 PDM; if publication comes before the decision, the new plan generally applies. In Guimarães, a PIP is worth it when:

  • The plot is on developable land in the 2015 PDM, or changes class or category in the approved revision.
  • You want to use the new parameters for low-density urban areas or rural settlements and need to know when they apply to your plot.
  • You want to build on agricultural or forest land or in a scattered building area.
  • The property touches the RAN, the REN, a flood zone or listed heritage.
  • You are buying and want to make the promissory contract conditional on the answer: see PIP before buying land. Apto Group prepares and follows up the PIP in Guimarães.

09 Frequently asked questions

Which PDM is in force in Guimarães?

The 1st revision, published as Aviso n.º 6936/2015 in the Diário da República on June 22, 2015, and in force since June 23, 2015, with the 2019, 2020 and 2021 amendments. The 2nd revision was approved in September 2026, but it only takes effect the day after publication in the Diário da República.

Is the new Guimarães PDM in force yet?

Not yet. The Assembleia Municipal approved the 2nd revision on September 28, 2026, and as of November 1, 2026, we could not find its publication in the Diário da República. Until then, the 2015 PDM applies.

Where can I check the Guimarães PDM online?

On the council's WebSIG (sig.cm-guimaraes.pt), which has modules for the PDM in force and for the revision and issues maps for planning applications. The "PDM em Vigor" page on the council's website lists the notices published in the Diário da República.

Does my plot become urban with the new PDM?

Only the revision's zoning map can show it. The approved draft adds 1,148.06 hectares of urban land, mostly as low-density urban areas, but abolishes developable land. Compare both maps on the WebSIG, and remember the new zoning only counts once it is published.

Can I build a house on agricultural land in Guimarães?

The 2015 PDM allows a single-family home in agricultural areas with prior authorization from the competent authority, a floor area ratio of 0.025 and a facade up to 7 m. These areas match the RAN soils, so the RAN regime also applies. A PIP confirms your specific case.

Is a PIP approved under the 2015 PDM still valid after the revision?

Yes, while it is within its validity period: the approved regulations treat rights from favorable PIPs as pre-existing (article 47). Once it has expired, or for an operation different from the one assessed, the new plan applies.

10 Official sources consulted

The official sources are in Portuguese. Check the version in force before preparing a notice, project or application.

Want to find these guides more easily when you search on Google? Add Apto Group as a preferred source.

Related services. To apply to your property.

Keep reading.

Have a property in mind? Tell us your idea.

We reply within about 2 hours during business hours, then prepare a proposal for your project.

geral@aptogroup.eu

Porto · Portugal

Contact details and request details
What is your situation? *